Montana in shipyard 2
Work is progressing. We had hoped to be further along by now, but fortunately we have built in enough time.
The hull is now complete. It has been completely overhauled and is practically as good as new.
The mast step has been removed and will be replaced with a new one in duplex stainless steel. Unfortunately this is necessary for certification reasons, although the old one still looked quite good.
Once the new mast step is in place, work will be carried out on the installations, engine and electrics.